Remote Australia Roads Upgrade
Objective
Ensure graders and excavators stay active by cutting bolt‐kit lead times from eight weeks to under a month.
Approach
-
Established a quarterly sea-and-rail shipping schedule with buffer stock warehoused in Perth.
-
Supplied complete M24 8.8 and M30 B7 bolt-and-nut kits, each batch accompanied by certificates of origin.
-
Rolled out digital inventory alerts so the customer received reorder reminders before stocks ran low.
Outcome
-
Lead time shrank consistently from 8 weeks to 3 weeks.
-
Fleet availability climbed 20 percent, from 75 percent up to 95 percent.
-
Administrative workload dropped by 30 hours per month thanks to automated tracking and fewer emergency orders.
Client
A government road-maintenance contractor operating 500 km from the nearest port in Outback Western Australia.